Muddy water pours from the mouth of a corrugated metal culvert pipe set in an eroded dirt bank.

Stormwater & Erosion Control

Stormwater Calculations

Runoff, infiltration and drainage sizing in one signed report, prepared to your agency's criteria for plan check.

What are stormwater calculations?

A stormwater calculation package is the engineering analysis that estimates how much rain runs off a site and sizes the trenches, basins, Low Impact Development (LID) facilities and pipes that capture, treat or carry it for agency review.

Agencies may call it drainage calculations, a drainage report, hydrology study, or hydrology and hydraulics (H&H) calculations. It goes in with a grading, building or improvement permit.

It is not a SWPPP: a stormwater pollution prevention plan controls sediment and other pollutants during construction, while these calculations size permanent drainage.

What's included in stormwater calculations

Scope follows your agency's drainage manual. A typical package includes:

  • Drainage area map

    Tributary areas, flow paths and hard and landscaped surfaces mapped for each discharge point.

  • Hydrology calculations

    Peak flows and runoff volumes for the design storms your agency's drainage manual specifies.

  • Facility sizing

    LID facilities, leach trenches, basins and pipes sized, with capacity and drawdown checks.

  • Signed & sealed report

    Methods, inputs and results in one report, formatted for plan check or state permit filing.

When do you need stormwater calculations?

Plan check asks for them when a project changes how water leaves the site.

  • Grading and building permits

    Grading or new paving changes how a site drains. See grading plans.

  • Crossing the LID threshold

    Projects that reach their municipal permit's impervious-surface threshold need LID; plan it into the site layout.

  • Lots with no storm drain

    Without a storm drain nearby, runoff may have to stay on site in trenches or basins.

  • Subdivisions, streets and storm drains

    Tentative maps and improvement plans often need tributary areas, pipe sizes and basin volumes.

How stormwater calculations are prepared

Five steps from site data to a sealed report.

  1. Confirm the agency's criteria

    We confirm the drainage manual, permit program and design storms, and gather the site plan, soils report and agency comments.

  2. Map the tributary areas

    Drainage areas and flow paths are mapped from a topographic survey, and roof, paving and landscape areas are measured.

  3. Run the hydrology

    Peak flows and volumes use the agency's method and rainfall data: often the Rational Method (Q = CiA) for small areas, a unit hydrograph for larger ones.

  4. Size the facilities

    Facilities are sized and checked for capacity, drawdown and hydraulic grade line, using measured infiltration rates where water soaks in.

  5. Coordinate, seal and respond

    Results feed the grading and improvement plans; the engineer in responsible charge seals the report and answers plan-check comments.

Types of stormwater calculations

Most packages combine several of these.

Leach trench design

A stormwater leach trench (infiltration trench) is a gravel-filled trench, often with perforated pipe, that holds runoff until it soaks in. Design volume, gravel voids and the infiltration rate at trench depth set its size. Septic leach lines are a separate septic design.

  • Drawdown checked against local limits and state health guidance to drain within 96 hours
  • Setbacks from foundations, septic fields and wells, and groundwater separation

Drainage basin design

A retention basin holds runoff until it soaks in or evaporates; a detention basin stores it and releases it slowly through an outlet. Calculations set storage volume, outlet size, spillway and freeboard for local design storms.

  • Routing to keep post-project peaks at or below pre-project peaks where required
  • Surface basins or underground vaults, chambers and oversized pipes

Post-construction / Low Impact Development (LID) calculations

LID calculations show how a project retains or treats runoff from new and replaced hard surfaces with bioretention, infiltration, harvesting or pervious paving. Under the statewide Small MS4 (municipal separate storm sewer system) permit, they cover:

  • Treatment volume or flow per Drainage Management Area (DMA); bioretention may be sized at 4% of tributary impervious area
  • Peak-flow (hydromodification) control for projects that create or replace an acre or more of impervious surface and increase impervious area

Pipe sizing calculations

Pipe sizing calculations confirm that storm drains, inlets and culverts carry the design flow: Manning's equation for capacity, and a hydraulic grade line check that water stays below grates and covers.

  • Slope, velocity, size and cover to the local standard
  • An overland release path for larger storms

Tributary area calculations

A tributary area is all the land, on site and off, that drains to one inlet, pipe, trench or basin; its surfaces set the runoff every other calculation uses.

  • Off-site run-on from upslope lots and streets
  • Runoff coefficient and time of concentration per area

California requirements for stormwater calculations

State law, two statewide permits and federal injection-well rules set the baseline:

  • Bus. & Prof. Code §6731, §6735, §6737

    Prepared under a licensed civil engineer

    California law counts the design of drainage and flood-control works as civil engineering (§6731). A licensed civil engineer prepares the calculations or is in responsible charge of them, and signs, seals and dates the final set (§6735). Licensed architects practicing architecture are exempt (§6737).

  • Order WQ 2013-0001-DWQ §E.12

    LID for 5,000 square feet or more

    Under the statewide Small MS4 permit (in effect as of September 2026), most projects creating or replacing 5,000 square feet or more of impervious surface must use LID, sized for roughly the 85th percentile 24-hour storm or a rainfall intensity of at least 0.2 inches per hour.

  • Order WQ 2022-0057-DWQ §IV.N

    Construction permit sites file calculations

    Except for linear underground and overhead projects, sites under the Construction General Permit upload post-construction plans and calculations to SMARTS, the state's online permit system. Where no local MS4 standard applies, the site must match its pre-construction runoff volume up to the 85th percentile 24-hour storm.

  • 40 CFR §144.3, §144.24, §144.26

    Buried infiltration can be a Class V well

    Perforated pipe that spreads stormwater underground is a subsurface fluid distribution system, which federal rules treat as a Class V injection well. EPA Region 9 requires California owners to register these wells; systems serving single-family homes need not register unless used by a home-based business.

Requirements vary by city and county: Phase I areas (larger cities and counties) and Central Coast agencies follow Regional Water Board rules, and local manuals set design storms. A July 2026 draft Small MS4 permit is not adopted as of September 2026.

Sources & references
  1. Phase II Small MS4 General Permit, Order WQ 2013-0001-DWQ (conformed), Section E.12 (State Water Resources Control Board)
  2. Construction Stormwater General Permit, Order WQ 2022-0057-DWQ, Section IV.N Post-Construction Requirements (State Water Resources Control Board)
  3. Business and Professions Code §6735, civil engineering documents (California Legislative Information)
  4. 40 CFR §144.3, definitions of "well" and "subsurface fluid distribution system" (Electronic Code of Federal Regulations)
  5. Underground Injection Well Registration Requirements, EPA Region 9 (U.S. Environmental Protection Agency)

Last reviewed .

Stormwater calculation FAQs

Who can prepare stormwater calculations in California?

Stormwater calculations for drainage facilities are civil engineering under California law (Business and Professions Code §6731). The calculations must be prepared by, or under the responsible charge of, a licensed civil engineer, who signs and seals the final report (§6735). Licensed architects practicing architecture are exempt from engineering registration (§6737), and small-project applicants use a State Water Board calculator to quantify site design measures.

When does a California project need LID calculations?

LID calculations are needed when a project crosses the threshold in its municipal stormwater permit. Under the statewide Small MS4 permit, that means 5,000 square feet or more of new or replaced impervious surface. Detached single-family homes that are not part of a larger plan of development are excluded but need site design measures from 2,500 square feet. Phase I permits and Central Coast agencies set their own thresholds.

Do stormwater calculations include infiltration testing?

Stormwater calculations use measured infiltration rates wherever water soaks in, but the testing is a separate field task. It is done at trench or basin depth by a method and professional the agency accepts, often a geotechnical engineer. The proposal states whether testing is included.

What affects the cost and schedule of stormwater calculations?

The cost and schedule of stormwater calculations depend on site size, the number of drainage areas and off-site run-on, the agency's manual, which requirements apply (LID, peak-flow control or flood routing), infiltration testing and plan-check rounds. Share the site plan, topographic survey, soils report and agency comments; the proposal then sets scope and timing.

Explore all Stormwater & Erosion Control services

Related projects

See all past work

Stormwater Calculations

Need stormwater calculations in California?

Send the site plan, any soils report and your agency's comments. We'll confirm which drainage manual and permit criteria apply before the analysis starts.